cfc
Structural
- Dec 26, 1998
- 11
A steel erector has asked to review a mezzanine project that involves recently installed composite beam framing where the steel anchor studs were installed along the deck's high flute. We have 3" concrete over 1 1/2"x18 ga composite deck (4 1/2" slab) with 3/4"x4" headed studs. In this situation, the deck is parallel to the supporting W12x19 beam.
The deck was installed with the studs installed afterwards. Holes were cut in the high flute to allow stud installation. The erectors then installed duct tape around the high flute stud opening. Concrete is yet to be placed.
Please review ti the attached pictures.
Thanks in advance for anyone's comments or thoughts.
The deck was installed with the studs installed afterwards. Holes were cut in the high flute to allow stud installation. The erectors then installed duct tape around the high flute stud opening. Concrete is yet to be placed.
Please review ti the attached pictures.
Thanks in advance for anyone's comments or thoughts.