Hi everyone,
Currently, I'm working on the addition to an existing mezzanine. The existing floor framing system consists of FSD composite concrete deck, composite filler beams and girders.
I am planning to utilize the same framing system for the new addition by adding one new girder parallel to the existing perimeter girder and filler beams span between the mentioned girders. I am aware that I may have to reinforce the existing girder to accomodate the new loads.
And following are my questions
1. What would it be the effective width of the existing girder in proposed condition (by adding a concrete deck to its side)? or in other words, should I utilized the minimum of 1/8 beam span and 1/2 beam spacing because of the addition of concrete deck for capacity calculation?
2. If yes, should the new concrete deck be tied into the existing? Dowel or ..?(FS Deck is parallel with girder)
3. I also have to fill large opening in the existing mezzanine with concrete deck, where new FSD will run perpendicular to existing perimeter filler beams. Again, can I tie the new concrete deck to the existing to obtain a wider effective width instead of adding a new beam parallel with the existing to catch the egde of new deck?
Thank you in advance for any recommendation.
Regards,
hdn32.
Currently, I'm working on the addition to an existing mezzanine. The existing floor framing system consists of FSD composite concrete deck, composite filler beams and girders.
I am planning to utilize the same framing system for the new addition by adding one new girder parallel to the existing perimeter girder and filler beams span between the mentioned girders. I am aware that I may have to reinforce the existing girder to accomodate the new loads.
And following are my questions
1. What would it be the effective width of the existing girder in proposed condition (by adding a concrete deck to its side)? or in other words, should I utilized the minimum of 1/8 beam span and 1/2 beam spacing because of the addition of concrete deck for capacity calculation?
2. If yes, should the new concrete deck be tied into the existing? Dowel or ..?(FS Deck is parallel with girder)
3. I also have to fill large opening in the existing mezzanine with concrete deck, where new FSD will run perpendicular to existing perimeter filler beams. Again, can I tie the new concrete deck to the existing to obtain a wider effective width instead of adding a new beam parallel with the existing to catch the egde of new deck?
Thank you in advance for any recommendation.
Regards,
hdn32.