Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Compressed Hydrogen Receiver

Status
Not open for further replies.

Leclerc

Chemical
Aug 22, 2002
73
Our process reaction uses a continuous stream of hydrogen, compressed to 90 barg from an OSBL source. We need to install a 20 m3 compressed hydrogen receiver between the compressor and the reactor.

In the first instance, where should I go to obtain a list of design points/ issues concerned with such a receiver?

regards,
Leclerc
 
Replies continue below

Recommended for you

Might want to post this in the Boiler and Pressure vessel forum also. My feeling is that from a design/fabrication point of view, they would likely have more input.
 
TD2K feeling is exactly right, you will need special material and testing procedure to take care of hydrogen induced cracking.

Good luck.

 
Its the process design that I'm concerned about - not the mechanical design.

Something along the lines;

Hydrogen in:- I'll need a pipe.
Hydrogen out:- Same pipe will probably do.
Pipe top or bottom:- not critical, but go for top.
Isolation valve between tank and pipeline:- not critical.
Tank will need to be strong enough or relief required:- go for strength.
Tank requires to be inspected:- manholes required.blow-down to safe place, purging and sweetening (plus reverse procedure)
Tank requires to be tested in-situ:- leak and pressure testing? Would lead to small branches for testing fluids and drainage; oh, and pressure gauges.
etc.,
etc..

Safety issues of 20 m3 of 90 bar H2?

 
you need a design to ASME V111 div 1 or maybe 2, you will need a relief valve - strong is not enough. the fabrication quality will need to be good, Hydrogen permeates through the plate and if there are voids ie weld defects they will collect the hydrogen , increase in prssure, and bulge/crack the steel
a HIC Hydrogen Induced Cracking resistant steel is recommended. The flange faces will need to have good sealing capabilities . all pipes welded no screwed connections or all your hydrogen will run away ..if it doesn't catch fire first
Sensitive leak test is a must in my book before the hydrotest..refer ASME V111like the other guys said...good luck...get experienced fabricators , no pick-up truck cowboys [ponder]

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor