SCGeo
Geotechnical
- Jun 9, 2005
- 20
Hello all,
I work for a small firm and help manage our geotechnical and materials (concrete, mortar, grout, structural steel) testing among other things. I am an EIT, with just about a year's worth of experience.
We are handling the materials testing for a large retail center. Type S (1800 psi) mortar is being placed between CMU's. 2''x 4'' cylinders are being constructed with sample mortar and cured for 28 days at 100% RH in a water/lime bath. Initially we were getting breaks well in excess of 3000 psi but I have just completed 2 sets that broke under strength (1550 psi and 1500, respectively.) I have checked the calibration of the break machine, observed the mixing process on site, used different capping mechanisms, etc..
I wasn't able to discern any difference in the mixing process on site, nor the temperature of the samples.
My question is, could the handling of the samples between the site and lab, or doing a sloppy job of constructing the cylinders or other factors account for such a difference?
With low concrete breaks I have always been able to pinpoint a factor such as temperature, adding too much water onsite, problems with the mix design etc. that would be a likely cause. I want to have done everything in my power to ensure that things were being done correctly on our end before we have to recommend remediation measures.
Anybody experienced this before?
I work for a small firm and help manage our geotechnical and materials (concrete, mortar, grout, structural steel) testing among other things. I am an EIT, with just about a year's worth of experience.
We are handling the materials testing for a large retail center. Type S (1800 psi) mortar is being placed between CMU's. 2''x 4'' cylinders are being constructed with sample mortar and cured for 28 days at 100% RH in a water/lime bath. Initially we were getting breaks well in excess of 3000 psi but I have just completed 2 sets that broke under strength (1550 psi and 1500, respectively.) I have checked the calibration of the break machine, observed the mixing process on site, used different capping mechanisms, etc..
I wasn't able to discern any difference in the mixing process on site, nor the temperature of the samples.
My question is, could the handling of the samples between the site and lab, or doing a sloppy job of constructing the cylinders or other factors account for such a difference?
With low concrete breaks I have always been able to pinpoint a factor such as temperature, adding too much water onsite, problems with the mix design etc. that would be a likely cause. I want to have done everything in my power to ensure that things were being done correctly on our end before we have to recommend remediation measures.
Anybody experienced this before?