Zambo
Civil/Environmental
- Jun 5, 2003
- 697
I am interested in board members views about concrete cover and construction joints.
Over the years if the drawings show either a column penetrating into a slab or beam or a bored pile penetrating into a pilecap I would allow the horizontal bars to sit directly onto the construction joint.
For clarity if this was a pilecap with specified 75mm cover to the bottom layer of rebar I would have the pile cut off at +75mm then place the first layer of rebar directly on the bored pile. But I am now on a project (still at design stage) where the designer is insisting that spacer blocks of minimum 50mm must be placed on the top of the cut off pile. This means that to satisfy the condition of pile cut off 75mm above the pile cap base then I must have 75 + 50mm = 125mm cover (although tbe specified cover is min 75mm).
Is there a correct way of doing this or is it variable depending on interpretation?
Over the years if the drawings show either a column penetrating into a slab or beam or a bored pile penetrating into a pilecap I would allow the horizontal bars to sit directly onto the construction joint.
For clarity if this was a pilecap with specified 75mm cover to the bottom layer of rebar I would have the pile cut off at +75mm then place the first layer of rebar directly on the bored pile. But I am now on a project (still at design stage) where the designer is insisting that spacer blocks of minimum 50mm must be placed on the top of the cut off pile. This means that to satisfy the condition of pile cut off 75mm above the pile cap base then I must have 75 + 50mm = 125mm cover (although tbe specified cover is min 75mm).
Is there a correct way of doing this or is it variable depending on interpretation?