I am working on a project in which concrete cube samples were taken. Tests were carried out at 3,7,28 days, the specified strength was 4000psi. Unfortunately the samples were not placed in a water for curing. After crushing samples at 28 days, the strength were much lower that 4000psi. Can the contractor be blamed for producinng concrete below the specified strength. Is there anyway of apply a factor to indicate what the strength would have been in an ideal condition.?