sybie99
Structural
- Sep 18, 2009
- 150
Hi Guys
I have in the past seen concrete being pired on slopes, generally not an issue, just reduce the slump. I have a case where the slope is 2:1, i.e. 2m horiz/1m vertical. Could this be problematic and what tips could you offer for pouring on a slope.
In this case the slab is 15m long on the slope from top to bottom.