ansys54
Civil/Environmental
- Mar 28, 2003
- 21
We have a 60' dia tank. From the base working up is a concrete base slab, welded steel tank bottom, 3' of granular fill and a 6" slab on a 30 degree incline toward the centre of the tank.
At approx. 17' out radially from the centre of the tank, the concrete slab has bulged up about 2'. It looks like a berm, gently sloping up and then back down. We cored holes and found the concrete slab has lifted leaving a void between the granular material and underside of slab.
Generally, the head of chemical in the tank is 12' above the elevation of the slab at the area in question.
Core samples showed a supersaturated granular material so we know the chemical is getting under the slab and being trapped by the steel tank liner below.
What could make the concrete heave up like this?
At approx. 17' out radially from the centre of the tank, the concrete slab has bulged up about 2'. It looks like a berm, gently sloping up and then back down. We cored holes and found the concrete slab has lifted leaving a void between the granular material and underside of slab.
Generally, the head of chemical in the tank is 12' above the elevation of the slab at the area in question.
Core samples showed a supersaturated granular material so we know the chemical is getting under the slab and being trapped by the steel tank liner below.
What could make the concrete heave up like this?