PEinVA
Structural
- Nov 15, 2006
- 321
I'm almost 2 years out of school and our office has a small steel building (5 stories) starting construction soon. I'll be the CM for our office for the job, with my boss always available for me. I haven't been involved in specifications much for my work here so far, only some for repair work in a PT situation, but not really for a job this size for new construction. Can someone give me some advice on the following questions submitted in response to the project specs.
Thanks!
1. Section 03100-3, 2.2, C, 1, 2, and 3. is it acceptable to substitute corner chamfer materials manufactured by other manufacturers and that wood chamfers can be provided in lieu of poly vinyl chloride (PVC) strips, steel or fiberglass?
2. Section 03100-4, G, 1, 2, 3, and 4. Is it acceptable to provide industry wood formed keys as an option manufactured from steel or metal for slab on grade construction joints and contraction joints? Slab on grade contraction joints will be provided using “soff cut technology”.
3. Section 03100-5, 3.2, D. “Removable Panels” (Inspection Pockets) will not be provided in walls, columns etc. to facilitate cleaning, drainage, and inspection. All formwork to be cleaned using compressed air or water prior to the satisfaction of the on-site testing and inspection representative in accordance with industry standard practice. Is this acceptable?
4. Section 03100-5, 3.3, C, a. Class A Form Surfaces Finish are assumed to be required at form surfaces exposed to view from outside the building. Class B Form Surface Finish will be provided in Parking Garage Areas and Stairs. Please confirm.
5. Section 03100-7, 3.3, H, I, and J. Our concrete subcontractor intends to propose alternates to specified stripping time limitations. CCC will submit an engineered shoring and stripping sequence for approval as specified. Industry Standard Practice will be followed.
6. Section 03310-2, 1.4, B. Because of industry and regional shortages, providing single source concrete, cementitious materials, sand, aggregates, and admixtures can not be guaranteed. Is this acceptable?
7. Section 03310-7, 2.3, C, 1, 2, 3, and 4. We have assumed slump limits will be changed. Minimum slump to be changed to 4” +/- 1” for concrete not containing HRWR. Slump limits of maximum 8” for concrete containing HRWR. Is this acceptable?
8. Concrete subcontractor will submit a plan for approval of slab on metal deck construction joints. Joint locations may exceed the limit specified in one or more directions. Clark will consult with the E.O.R. on joint layouts for approval. (FYI only)
9. Section 03310-15, 3.6, A. Temporary protection of concrete form construction traffic, weather or mechanical abrasion for fourteen (14) days after placing is extremely difficult to ensure and beyond our standard operating practice. Clark will provide standard protection of concrete for initial curing period or seven (7) days. Please confirm this is acceptable.
10. Section 03310-15, 3.6, B. Protection of exposed concrete form staining can be provided to the extent that we can control our operations, eg limit vehicle traffic, storage of materials, etc. However, we can not limit any staining originating from the environment, specified mixes, or elements beyond our control. Please confirm acceptability.
I appreciate any input guys!
RC
RC
All that is necessary for the triumph of evil is that good men do nothing.
Edmund Burke
Thanks!
1. Section 03100-3, 2.2, C, 1, 2, and 3. is it acceptable to substitute corner chamfer materials manufactured by other manufacturers and that wood chamfers can be provided in lieu of poly vinyl chloride (PVC) strips, steel or fiberglass?
2. Section 03100-4, G, 1, 2, 3, and 4. Is it acceptable to provide industry wood formed keys as an option manufactured from steel or metal for slab on grade construction joints and contraction joints? Slab on grade contraction joints will be provided using “soff cut technology”.
3. Section 03100-5, 3.2, D. “Removable Panels” (Inspection Pockets) will not be provided in walls, columns etc. to facilitate cleaning, drainage, and inspection. All formwork to be cleaned using compressed air or water prior to the satisfaction of the on-site testing and inspection representative in accordance with industry standard practice. Is this acceptable?
4. Section 03100-5, 3.3, C, a. Class A Form Surfaces Finish are assumed to be required at form surfaces exposed to view from outside the building. Class B Form Surface Finish will be provided in Parking Garage Areas and Stairs. Please confirm.
5. Section 03100-7, 3.3, H, I, and J. Our concrete subcontractor intends to propose alternates to specified stripping time limitations. CCC will submit an engineered shoring and stripping sequence for approval as specified. Industry Standard Practice will be followed.
6. Section 03310-2, 1.4, B. Because of industry and regional shortages, providing single source concrete, cementitious materials, sand, aggregates, and admixtures can not be guaranteed. Is this acceptable?
7. Section 03310-7, 2.3, C, 1, 2, 3, and 4. We have assumed slump limits will be changed. Minimum slump to be changed to 4” +/- 1” for concrete not containing HRWR. Slump limits of maximum 8” for concrete containing HRWR. Is this acceptable?
8. Concrete subcontractor will submit a plan for approval of slab on metal deck construction joints. Joint locations may exceed the limit specified in one or more directions. Clark will consult with the E.O.R. on joint layouts for approval. (FYI only)
9. Section 03310-15, 3.6, A. Temporary protection of concrete form construction traffic, weather or mechanical abrasion for fourteen (14) days after placing is extremely difficult to ensure and beyond our standard operating practice. Clark will provide standard protection of concrete for initial curing period or seven (7) days. Please confirm this is acceptable.
10. Section 03310-15, 3.6, B. Protection of exposed concrete form staining can be provided to the extent that we can control our operations, eg limit vehicle traffic, storage of materials, etc. However, we can not limit any staining originating from the environment, specified mixes, or elements beyond our control. Please confirm acceptability.
I appreciate any input guys!
RC
RC
All that is necessary for the triumph of evil is that good men do nothing.
Edmund Burke