DocDirt
Geotechnical
- Dec 6, 2007
- 29
How long should the hole be left open after drilling and before concreting?
The job involves a friction caisson with a socket in Shale rock. Shale tends to slake and weather on soaking. I was told that the practice in some states dictates that an open excavation should not be allowed to stand for more than 4 days or so.In this project, the hole is filled with water to balance the hydrostatic pressures in the hole. We sre going to run some durability tests on Shale.
DocDirt
The job involves a friction caisson with a socket in Shale rock. Shale tends to slake and weather on soaking. I was told that the practice in some states dictates that an open excavation should not be allowed to stand for more than 4 days or so.In this project, the hole is filled with water to balance the hydrostatic pressures in the hole. We sre going to run some durability tests on Shale.
DocDirt