HEHurst
Civil/Environmental
- Oct 1, 2008
- 24
I'm working on a plan that includes the need to connect a new subsurface drain line (likely 8" PVC) to an existing 18" concrete storm sewer. There is no manhole at the connection location, and a new one cannot be placed there.
So I believe the best option for making the connection is to expose the top and/or side of the 18" storm sewer and have the contractor simply drill out a hole to tap into with the PVC (depending on final design, will either come straight into the side with the PVC pipe or drop down from the top with a fitting).
Is it reasonable to assume that most underground/utility contractors will have the equipment to drill through the concrete storm sewer? (this connection will likely be the only concrete work on the job) I'm assuming some sort of diamond-blade hole saw is used, right? Is the same sort of saw also able to cut through rebar if encountered? (don't know if the storm sewer is reinforced or not, so I'll assume it is)
Would some sort of grout be used to hold the PVC in place in the storm sewer opening? Any recommendations on specs for the grout? I imagine it's key when cutting the opening in the storm sewer to minimize the gap between the outside wall of the PVC pipe and the opening in the concrete.
I probably will have this connection be a separate bid item in the construction contract. Any guidance on typical unit prices to expose the concrete storm sewer (it's about 4 feet deep, under grass), drill through it, and connect the PVC drain pipe)? There will just be one of these connections on the job. Or would this typically be "incidental" to installing the rest of the PVC pipe?
Thanks!
So I believe the best option for making the connection is to expose the top and/or side of the 18" storm sewer and have the contractor simply drill out a hole to tap into with the PVC (depending on final design, will either come straight into the side with the PVC pipe or drop down from the top with a fitting).
Is it reasonable to assume that most underground/utility contractors will have the equipment to drill through the concrete storm sewer? (this connection will likely be the only concrete work on the job) I'm assuming some sort of diamond-blade hole saw is used, right? Is the same sort of saw also able to cut through rebar if encountered? (don't know if the storm sewer is reinforced or not, so I'll assume it is)
Would some sort of grout be used to hold the PVC in place in the storm sewer opening? Any recommendations on specs for the grout? I imagine it's key when cutting the opening in the storm sewer to minimize the gap between the outside wall of the PVC pipe and the opening in the concrete.
I probably will have this connection be a separate bid item in the construction contract. Any guidance on typical unit prices to expose the concrete storm sewer (it's about 4 feet deep, under grass), drill through it, and connect the PVC drain pipe)? There will just be one of these connections on the job. Or would this typically be "incidental" to installing the rest of the PVC pipe?
Thanks!