Hi,
For consolidation testing, are the T50 and T90 constants both usable when calculating Cv or is one result more accepted than the other. I usually see the results expressed using T90 (i.e., Cv(90))
Thanks in advance.
D
For consolidation testing, are the T50 and T90 constants both usable when calculating Cv or is one result more accepted than the other. I usually see the results expressed using T90 (i.e., Cv(90))
Thanks in advance.