hvacpiper
Mechanical
- Apr 14, 2011
- 16
This is a general question posed to the mechanical engineers on here, about constructability of design,and who is inherintly responsible for it.Some background first,I'm just a dumb plumber,I'm not a contractor,I just install pipe for a living, at an hourly rate.That being said, after spending years going through construction documents......Who deserves the blame for documents that cannot be built?
At a recent ASPE meeting I attended,a question was posed to the panel asking ,who the ultimate responsibility lies with,to ensure a system can be constructed and installed per design.The AIA guidelines were mentioned,and that most engineering firm's designs "should" adhere to the "AIA Guidelines".I have not yet been able to read through said documents,and I wonder,if they do in fact place responsibility on anyone's shoulder.Being the end user of construction documents,I feel as though,I am proctoring dialogue between engineers and architects,that should have happened long before,I,the pipefitter was going to drill a 5" hole to put a 4" pipe in a 3-5/8" stud wall.
So is it, Architects lack of knowledge of construction methods and materials? Or is it the Engineers who place 4" risers in 4" walls? I'm going to assume it's the architects,but I'm curious as to how much back and forth the disciplines actually have in the design end of construction.4" pipe in a 4" wall is an over-simplification,but I do see that quite often,even from AE firms...
At a recent ASPE meeting I attended,a question was posed to the panel asking ,who the ultimate responsibility lies with,to ensure a system can be constructed and installed per design.The AIA guidelines were mentioned,and that most engineering firm's designs "should" adhere to the "AIA Guidelines".I have not yet been able to read through said documents,and I wonder,if they do in fact place responsibility on anyone's shoulder.Being the end user of construction documents,I feel as though,I am proctoring dialogue between engineers and architects,that should have happened long before,I,the pipefitter was going to drill a 5" hole to put a 4" pipe in a 3-5/8" stud wall.
So is it, Architects lack of knowledge of construction methods and materials? Or is it the Engineers who place 4" risers in 4" walls? I'm going to assume it's the architects,but I'm curious as to how much back and forth the disciplines actually have in the design end of construction.4" pipe in a 4" wall is an over-simplification,but I do see that quite often,even from AE firms...