Placing wall concrete is a balancing act. The Contractor wants to place the concrete as fast as possible to reduce labor costs, but fast placement increases formwork loading. The engineer wants the concrete placed fast enough to avoid a cold joint. Placed too fast, wall forms can bulge or breakout. Placed too slow and cold joints can develop when lower portions of the wall reach their initial set before the upper layers are placed.
Placing temperture and mix design have a major effect on concrete's initial set time and on shrinkage stresses.
Mary Hurd's book "Formwork for Concrete" has many good suggetions and details for concrete wall forming and placing, including a table of placement speed vs. formwork loading.
A 40' long section of 12" wall, 10' high contains 14.8 cy of concrete, which is basically two ready-mix truck loads. If it is placed at the rate of 5'/hr, then it takes 2 hours.
Placing stronger wall ties at the bottom section of the wall forms allows a faster pour rate.
Equipment makes a big difference in placing time too. Is the concrete placed by chute directly into the forms, with a pump or bucket or conveyor?