Laplacian
Electrical
- Jul 15, 2002
- 246
What is a general rule of thumb for coordination timing between the time-overcurrent clearing for main and tie breakers operating in a spot network configuration? If I add 0.3 seconds for every downstream device on our 13.2kV feeder, clearing time becomes significant at the mains.
This is our main substation utility interface at 13.2kV. The utility owns the transformers (69-13.2kV) and they do have transformer differential and directional relaying looking into our system.
Also, are there any good freely published documents regarding basic/advanced industrial relay coordination?
This is our main substation utility interface at 13.2kV. The utility owns the transformers (69-13.2kV) and they do have transformer differential and directional relaying looking into our system.
Also, are there any good freely published documents regarding basic/advanced industrial relay coordination?