timm33333
Electrical
- Apr 14, 2012
- 198
In doing phase and ground coordination using ETAP, some TCC’s pass through the transformer damage curve and/or cable damage curve. Also some TCC’s mis-coordinate, which means that at one or two points the TCC of the upstream medium voltage fuse touches the TCC of downstream low voltage breaker. It looks that it is not possible to avoid these mis-coordinations. As the fuse upstream of the transformer is sized as per NEC, and also the cables are sized as per NEC, so I would assume that transformers and cables would be protected even if the TCC’s pass through the transformer/cable damage curves.
Is it normal to have some mis-coordination between the upstream devices and downstream devices at one (or two) points on TCC? Also is it normal that the TCC passes through the transformer/cable damage curves?
Is it normal to have some mis-coordination between the upstream devices and downstream devices at one (or two) points on TCC? Also is it normal that the TCC passes through the transformer/cable damage curves?