Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Core drill/insert spacing

Status
Not open for further replies.

EEJaime

Electrical
Jan 14, 2004
536
Hello all, that includes you Casseopeia,

I will ask the structural on this project this question, but thought it would be good to get this forum's input.

I have a situation where I will be penetrating a poured in place basement wall with a large quantity of conduit. These will mostly be 4" conduit, but I also have some 6" conduit and a few smaller ones. In one location for instance I have 16-6" conduit entering a basement from an on-site manhole. I intend to penetrate the wall either with core-drilled holes or by using a cast-in-place pvc insert. The 6" rigid steel conduit requires a 10" opening to allow the installatio of the link-seal assembly. I have given a sketch to the structural engineer indicting these penetrations in a 2 wide x 8 high configuration. So he will frame out a 10'-6" h x 2'-6" wide 'window' without rebar for the penetrations if I core drill, or we will cast the inserts in place.

OK, my question is this. I have indicated a 6" space horizontally and vertically between each 10" penetration. I assumed that this would be sufficient to allow working space to tighten the link-seals and prevent spauling of the openings if cored. What would your recommended minimum spacing between core-drilled openings be? Would that change if we used cast in place inserts?

Thank you for your patience, regards,

EEJaime

 
Replies continue below

Recommended for you

I would first see what the general spacing of the reinforcing is in the vertical and horizontal direction and try to accommodate that such that you would have a bar between each opening.

 
In any case for most basement walls/mats at these hole sizes no particular problem should develop; how less if acting with care and attention to detail. So continue in consultation with the director of the structural works and go ahead.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor