psychedomination
Structural
- Jan 21, 2016
- 123
Hi there,
I have a client that would like to create two 6” holes in an existing reinforced concrete basement foundation wall. I asked for the existing drawings and the only drawing in archives they were able to find is showing the reinforcement layout in the slab above, but in this same drawing it states the thickness of the wall as 10” and that it is reinforced concrete. However, the reinforcement size and layout is not known.
A 6” hole seems small to me in a reinforced concrete wall.
I am wondering if there is any guidance/rule of thumb for the maximum hole size in a wall, where considerations for additional structural framing/beams above are not necessary.
Logically I am thinking for a 6” hole, the load will just redistribute around it, however, I am unsure of the spacing requirements/best practice for this (what the minimum/maximum spacing should be between the holes). The client is digging a trench outside the building and running the two 6” pipe duct side by side. They said it didn’t matter if they were side by side horizontal or side by side vertical. I am thinking from a structural point of view it would be better to have them side by side vertical, as the interaction zone of the load above the hole would be smaller? Any comments on this would be helpful.
I was thinking they could just core through the wall without any temporary supports. Or perhaps they would need to do a 6" wide saw cut rectangle going down like 14" and drypack/fill with mortar when the pipe ducts are in position?
A photo of the site is below with a sketch of what I am thinking. I would like to get any advice or general guidance for situations like this and the associated literature link if possible that I can read for my own knowledge/confirmation.
I have a client that would like to create two 6” holes in an existing reinforced concrete basement foundation wall. I asked for the existing drawings and the only drawing in archives they were able to find is showing the reinforcement layout in the slab above, but in this same drawing it states the thickness of the wall as 10” and that it is reinforced concrete. However, the reinforcement size and layout is not known.
A 6” hole seems small to me in a reinforced concrete wall.
I am wondering if there is any guidance/rule of thumb for the maximum hole size in a wall, where considerations for additional structural framing/beams above are not necessary.
Logically I am thinking for a 6” hole, the load will just redistribute around it, however, I am unsure of the spacing requirements/best practice for this (what the minimum/maximum spacing should be between the holes). The client is digging a trench outside the building and running the two 6” pipe duct side by side. They said it didn’t matter if they were side by side horizontal or side by side vertical. I am thinking from a structural point of view it would be better to have them side by side vertical, as the interaction zone of the load above the hole would be smaller? Any comments on this would be helpful.
I was thinking they could just core through the wall without any temporary supports. Or perhaps they would need to do a 6" wide saw cut rectangle going down like 14" and drypack/fill with mortar when the pipe ducts are in position?
A photo of the site is below with a sketch of what I am thinking. I would like to get any advice or general guidance for situations like this and the associated literature link if possible that I can read for my own knowledge/confirmation.
