Dear mates,
Our contractor just finishes hydro test for pipeline 14" (thickness 11.9 mm length 2 km) , and start the rinsing water using foam pig.
The problem he can not start the purging with nitrogen immediately (logistic problem )
And hi proposes to make it after 2 months.
Its can be some risk of corrosion inside the pipe ?
Your advice please
Our contractor just finishes hydro test for pipeline 14" (thickness 11.9 mm length 2 km) , and start the rinsing water using foam pig.
The problem he can not start the purging with nitrogen immediately (logistic problem )
And hi proposes to make it after 2 months.
Its can be some risk of corrosion inside the pipe ?