CabreraR
Civil/Environmental
- May 26, 2012
- 2
I am working as cost engineer and something came to my table that really seems more a joke than a serious work. I received a man-hour estimate for a scope of work for producing a FEMA type flood map for 640 acres, the global stability analysis for 2.5 miles of levee, dam breach analysis, levee overtopping and many other assumptions showing about $64K.
I developed an estimate for $421K. Other has estimate that the study will be between $300 and $500K. Is anyone out there that can pitch a bull-pack number in term of cost and duration?
I developed an estimate for $421K. Other has estimate that the study will be between $300 and $500K. Is anyone out there that can pitch a bull-pack number in term of cost and duration?