Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Cost Estimating Method(s) for Public Infrastructure Projects

Status
Not open for further replies.

westend392

Civil/Environmental
Jan 17, 2006
17
Hi everyone, I just recently graduate and now working in a firm that concentrate in mostly Public Work related projects (transportation, water, sewer, storm drains, etc.) in SE USA (FL, GA, MS, LA). I'm having problem in deciding the approach that I need to take in preparing "Opinion of Probable Cost" report for our projects (currently water & sewer network). In school, we were introduced to Means Cost data book, but in reality, it seems that not to many people, in my office anyway, rely on Means Cost Data. It seems that we emphasize our efforts by using past projects' bid tab data as the basis of our estimating work. Many in the office claim that Means Cost unit prices are way too conservative. Is this true?

The problem is that the bid tab data that we have right now is sometime 3-4 years old and using some general inflation factor for all of the unit price seems to be too conservative. Sometime , we just don't have the data. Someone has suggested to contact the contractors directly but I don't know how responsive they will be in sharing their unit price info with me nor do I know how to adjust their price info to account for "front-loading" practice, etc. Any help will be greatly appreciated.
 
Replies continue below

Recommended for you

The best way to estimate new projects on a conceptual basis is to use historical project data and to escalate it. IF YOU USE a good escalation index that is relevant to your industry.

I use three cost indexes and average them. Then economies of scale adjustment must be applied. All historical data is entered into an excel spreadsheet and automatically adjusted and escalated by changing the new project size.

Using this method I have "adjusted" projects from the 1960's and derived at valid defensible estimates.
 
If you are interested in learning more you can join the AACE (Cost Engineering Professional Association)
Or my "how to" technical paper “Accurate Estimates in Less Than a Minute” which uses historical project data to estimate new projects, can be found here,

Presentation can be found here,

If neither of the above links works try,
and follow the links there
 
What do you guys think about "ENR Construction Cost Indexes"?
What are they? I've actually never seen them but one or two people that I know suggest using them as unit-price base.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor