I am working for the replacement of a old MicroZ for a new control system in a petrol refinery.
Have you any idea of the manhours for project design for:
1000 analog I/O
1000 digital I/O
including matériel specification , call for bid, purchasing, construction follow up, commissionning
thanks for you help
serge
Have you any idea of the manhours for project design for:
1000 analog I/O
1000 digital I/O
including matériel specification , call for bid, purchasing, construction follow up, commissionning
thanks for you help