Sirius
New member
- Jul 16, 2002
- 37
I have to estimate the cost (mainly man hours) of a project which is nearly nearly completed but has many many small problems.
The expectation I feel is that I present a WBS with work packages and associated costs.
But I think that it is not the right way to do, because it suggests that with standard everyday program management tasks the project could be well terminated.
And so I decided to have the following tenor for my presentation.
" ......
How to estimate the effort necessary for a 'nearly' completed project with many 'small' problems?
Forget (project history and experience) ==> Done
Estimate (a 'healthy' project) ==> Done
Cure (the project) ==> To Be Done
....."
In my presentation I give a rational for my Estimation
and a starting point to begin the Cure (unfortunately I have not the complete cure in mind, but I think that is not too bad because such a presentation serves also to define actions with other more experienced people, ... the bosses for instance...)
Now my question, how would you present the Cost To Complete for a nearly nearly completed project with many many small problems?
Looking forward to your answer
Best Regards
Sirius
The expectation I feel is that I present a WBS with work packages and associated costs.
But I think that it is not the right way to do, because it suggests that with standard everyday program management tasks the project could be well terminated.
And so I decided to have the following tenor for my presentation.
" ......
How to estimate the effort necessary for a 'nearly' completed project with many 'small' problems?
Forget (project history and experience) ==> Done
Estimate (a 'healthy' project) ==> Done
Cure (the project) ==> To Be Done
....."
In my presentation I give a rational for my Estimation
and a starting point to begin the Cure (unfortunately I have not the complete cure in mind, but I think that is not too bad because such a presentation serves also to define actions with other more experienced people, ... the bosses for instance...)
Now my question, how would you present the Cost To Complete for a nearly nearly completed project with many many small problems?
Looking forward to your answer
Best Regards
Sirius