gmprox23
Civil/Environmental
- Aug 12, 2022
- 3
Hi to ALL,
I would just like to ask for tips and recommendations to do the above process to avoid damage to the interlocks during driving.
We're following NASSPA sheet pile guide, and did the following with these results:
- pulled with wire rope to reduce longitudinal lean from 2.7% to 2.2%
- fabricated our tapered piling to correct the 2.2% lean
Moving forward, we are thinking of:
#1 setting the pile
#2 with the hammer at center of gravity of piling, "drive to half the driven length"
#3 then drive rest of the way counteracting with hammer off center of piling
When do you do hammer counteracting in step #3? At 1/3 or 1/2 the driven length?
thanks and best regards,
gmprox23
I would just like to ask for tips and recommendations to do the above process to avoid damage to the interlocks during driving.
We're following NASSPA sheet pile guide, and did the following with these results:
- pulled with wire rope to reduce longitudinal lean from 2.7% to 2.2%
- fabricated our tapered piling to correct the 2.2% lean
Moving forward, we are thinking of:
#1 setting the pile
#2 with the hammer at center of gravity of piling, "drive to half the driven length"
#3 then drive rest of the way counteracting with hammer off center of piling
When do you do hammer counteracting in step #3? At 1/3 or 1/2 the driven length?
thanks and best regards,
gmprox23