bernoullies123
Mechanical
- Dec 30, 2009
- 203
Hi Peers,
I have a specification requirement that requires the purging gas to remain on until the completion of the weld. (CRA cladded pipe weld)
Now I would concur with purging for the root and hot pass and maybe even a couple of filler runs. But I do not understand why the gas would need to remain on for the full duration of the weld.
I wanted to turn off the gas after about 30% (5-8 layers) of the weld was completed but unfortunately I wasn't granted this request by the specification owner.
Appreciate any feedback as to your thoughts about any benefits for keeping the internal purge on until the joint is 100% welded.
I note that AWS D10.11 clause 6.3 says that it is normal practice to maintain the purge for the 2nd and 3rd layers.
The continuous purge will have significant implications as I'm assure you already understand (cost of gas, HSE, no in-process inspection internally etc.)
Thanks in advance.
I have a specification requirement that requires the purging gas to remain on until the completion of the weld. (CRA cladded pipe weld)
Now I would concur with purging for the root and hot pass and maybe even a couple of filler runs. But I do not understand why the gas would need to remain on for the full duration of the weld.
I wanted to turn off the gas after about 30% (5-8 layers) of the weld was completed but unfortunately I wasn't granted this request by the specification owner.
Appreciate any feedback as to your thoughts about any benefits for keeping the internal purge on until the joint is 100% welded.
I note that AWS D10.11 clause 6.3 says that it is normal practice to maintain the purge for the 2nd and 3rd layers.
The continuous purge will have significant implications as I'm assure you already understand (cost of gas, HSE, no in-process inspection internally etc.)
Thanks in advance.