Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations pierreick on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Cracking moment - AASHTO vs ACI vs PCI

Status
Not open for further replies.

amc806

Structural
Jan 5, 2024
1
I am currently working on a project with a prestressing / precasting fabricator to design roof beams for a large warehouse type building. The conceptual detail shown on the contract plans was for 48"wide x 33" deep voided rectangular adjacent box beams similar to many bridge structures. Majority of my experience is in bridge design and the design program I'm most familiar with is PennDOT/AASHTO based (PSLRFD).

Reviewing the design generated with that program, I found that the AASHTO cracking moment requirement (1.2*Mcr) was satisfied, but when back-checking against the ACI / PCI codes (both cited in the contract docs), I calculated an Mcr that was approximately 40% higher than what AASHTO calculates. This has BIG implications on the design and the amount of P/S steel in the beams. Any insight as to why the Mcr value prescribed by ACI and PCI (not identical but similar) is so much higher than that required by AASHTO? Or maybe my calculations / interpretation of the codes are incorrect?

Thanks!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor