OUe
Structural
- Feb 14, 2007
- 47
I'm designing a top-running bridge crane's runway beam and gantry tower support system. The bridge crane spans 94', the gantry towers (triangular lattice tower) span 25', 16', and 24'. Because I haven't designed a crane system in nearly 4 years, I am a little rusty. I have a radio/cab operated bridge crane, so I understand the impact loads to the runways, and I'm using AISC DG #7 with AISC 360-05 for ASD and top flange lateral/torsional/sidesway buckling.
There were a couple questions from the mechanical engineer who is the project manager. He is asking if the runway beam spans are ok and if they can make a nice 2-beam (interior splice in the middle of the 16' span).
1. I told him that I recall some rule of thumb about runway spans not allowed to exceed 20% of the adjacent span, but that I wasn't confident on it and I'd get back to him. I honestly can't remember why this rule of thumb is bothering me.
2. Secondly, I told him that I'd prefer not to design a splice at the mid-span and it would be counterintuitive to save on the cost of buying additional beams of 40' length. The cost of the connection (I wouldn't do anything less than a CJP moment connection) would cost more than the beams. I didn't even want to mention the fatique issues, but it is certainly a worthy concern.
I'm mostly looking for a clarification of number 1 above, but any additional comments would be great. THANKS! OUe
There were a couple questions from the mechanical engineer who is the project manager. He is asking if the runway beam spans are ok and if they can make a nice 2-beam (interior splice in the middle of the 16' span).
1. I told him that I recall some rule of thumb about runway spans not allowed to exceed 20% of the adjacent span, but that I wasn't confident on it and I'd get back to him. I honestly can't remember why this rule of thumb is bothering me.
2. Secondly, I told him that I'd prefer not to design a splice at the mid-span and it would be counterintuitive to save on the cost of buying additional beams of 40' length. The cost of the connection (I wouldn't do anything less than a CJP moment connection) would cost more than the beams. I didn't even want to mention the fatique issues, but it is certainly a worthy concern.
I'm mostly looking for a clarification of number 1 above, but any additional comments would be great. THANKS! OUe