Hi,
when I create a drawing of a big assembly the base view after the first view, NX calculate the projected view.
But if I want only one view, exist a single view command ?

Thank you...

Using NX 7.0.1.7 MP1 and TC8.1
 
Replies continue below

Recommended for you

Yes, goto customer defaults and search for base view.
Then you will see a check box that says "Automatically start projected view command". See att. picture.
Remove the check, restart nx and you will now have what you want.

Best regards,

Michaël.

NX4+TC9 / NX6+TC8Unified / NX7.5 native

 
 http://files.engineering.com/getfile.aspx?folder=a715ae12-a879-499c-84b1-8d3e989e9082&file=base_view.jpg