Hi All,
Now, we are using the aluminum formwork for slab/ beam for typical slab with 4 day for slab cycle (that means after 1 day we will striking formwork for slab but keep shoring).
Client require us to check the long-term deflection of slab due to early striking of formwork. They worry about the deflection due to creep.
As I found in ACI209.2R-08 code, the ultimate value of creep is 2.35 but the they required 7-days for curing.
So, how to determine the creep value of concrete after 1 day loading. Please advise.
Now, we are using the aluminum formwork for slab/ beam for typical slab with 4 day for slab cycle (that means after 1 day we will striking formwork for slab but keep shoring).
Client require us to check the long-term deflection of slab due to early striking of formwork. They worry about the deflection due to creep.
As I found in ACI209.2R-08 code, the ultimate value of creep is 2.35 but the they required 7-days for curing.
So, how to determine the creep value of concrete after 1 day loading. Please advise.