Whenever the critical path is calculated, it is calculated as the path with no slack that leads to the LAST (latest) task in the file. Is there any way to get the critical path for a task that is not the latest task?
Right now I'm doing it by deleting the later tasks, though I need to remember not to save the file after I do that!
thanks!
Right now I'm doing it by deleting the later tasks, though I need to remember not to save the file after I do that!
thanks!