kechha2060
Civil/Environmental
- Dec 8, 2007
- 26
I have a existing roadway culvert in zone AE. We are proposing improvement on the roadway (widening) but decided (higher officials) to leave in AE zone. Existing culvert is 2-60" pipes for 2.2k cfs flow at culvert. The 100yr flood elev (HEC-RAS) at the culvert determined is 4' above the pavement (different study). Do one has to design the culvert for the 2.2k cfs or can allow overtopping and hence fewer and smaller culvert sizes.