1964bhoy
Electrical
- Nov 28, 2006
- 3
Anyone able to help?..
Looking to monitor the loadings of a package S/S transformer to add more capacity.
Cannot access the LV small wiring without a shutdown so was proposing moving the open point in order to feed the intended transformer soley from this section of the 11kV ring.
Will this application cause failure to the Rogowski coil?..or even be achievable ..
Looking to monitor the loadings of a package S/S transformer to add more capacity.
Cannot access the LV small wiring without a shutdown so was proposing moving the open point in order to feed the intended transformer soley from this section of the 11kV ring.
Will this application cause failure to the Rogowski coil?..or even be achievable ..