DPAJR
Civil/Environmental
- Jul 8, 2006
- 74
I am working on a stormwater runoff project in a desert area. There are about 500 acres of mostly bare sandy desert. If I look up a curve number from a list nothing is an exact match but urban desert with CN = 63 looks close. However, when I use the "Available Water Capacity" from the NRCS map unit description with an S value of 1.8 inches and solve for CN in the equation S=(1000/CN)-10 I get a CN of about 85. The difference is a max flow of 40 cfs vs 120 cfs using HEC-HMS.
I was wondering which one would most of you choose?
Thanks
dpajr
I was wondering which one would most of you choose?
Thanks
dpajr