How to define Meter demand hourly usage in CYME? I have the hourly total metering upstream the feeder and not sure how can I put the data as a time-series for a meter.
If you are doing a load flow, normally you would only input the peak load for each feeder. That could be determined by finding the maximum of the hourly data.
I think you're going to need either long term dynamics or load flow with profiles module to do any time series stuff. You will also probably find more support on the Cyme forums.