Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

deadman anchorage

Status
Not open for further replies.

GeoGrouting

Civil/Environmental
Jun 24, 2007
65
0
0
CA
Some deadman anchorages are being designed. Are there any typical depth for the anchorage and what do you recommend(minimum) for depth of site investigation for the location of the deadman concrete elements.In a similar project in silty fine sand materials they advised 13' long x 2' deep x 3' wide concrete deadman buried 6' in the ground.

Am looking for a design manual that explains the typical values and how to calculate/estimate the pull-out load.

What is the recommended depth of site investigation for the above case history. I guess about 10'. Your advise would be appreciated.
 
Replies continue below

Recommended for you

Maybe I'm misunderstanding your statement, but it seems like you are trying to size the deadman before you know the loads on the wall. Determine the loads on the wall first, then size the deadman accordingly to mitigate those loads, plus an appropriate safety factor.

Attached is a US Army Corps of Engineers Design Manual for Sheet Pile Walls. It gives a procedure for designing a deadman anchor (Chapter 5, page 5-10). Make sure the deadman is behind the passive wedge of the wall!

 
 http://files.engineering.com/getfile.aspx?folder=eb49d3dd-2818-4ab1-8cb1-7fff9b8d9384&file=Design_of_Sheet_Pile_Walls.pdf
Also...

Unless you have a geotech report, you will be relegated to the allowable passive pressures of the IBC.

Mike McCann
MMC Engineering
Motto: KISS
Motivation: Don't ask
 
Status
Not open for further replies.
Back
Top