What sort of incremental deflection limits do you guys use for members supporting masonry?
In our Australian codes the suggested limit is Span/1000, or Span/500 where provision is made to minimise the effect of the movement (whatever that means!).
The senior guys in the office just say to use Span/500. I am keen to follow this advice given how hard it can be to get things to within Span/1000.
What are your thoughts?