Depth to Fixity - Pile in MSEW

Status
Not open for further replies.

Trouser

Structural
Jan 31, 2011
19
I am working on a foundation for a bridge over the interstate that requires the use of pile foundations through MSE walls that are approximately 30 feet in height. The structural design engineer in our unit is concerned about how the unbraced length of the pile will effect the axial capacity of the pile section. How is this unbraced length determined? Is it related to the depth to fixiity?

Typical details that I have seen for this foundation type include isolating the piles from the MSEW by placing CMP around the piles and backfilling with a loose/low strength material such as pea gravel.

Should the pile be considered unbraced through the entire MSEW or can the pea gravel be used in a typical depth to fixity calculation such as the one outlined in AASHTO LRFD 10.7.3.13.4?



 
Replies continue below

Recommended for you

the details you saw are for what is known as an integral abutment.
another consideration is the lateral load which the mse places on the piles within the abutment. please consult a geotechnical engineer.
 
I'd be very interested to know how this turns out or what you guys end up doing. Sorry that I don't have any insight.

Thanks.