Syahar1975
Mechanical
- Feb 3, 2011
- 224
Good morning Gents,
This issue always happen in tank construction in my past and current projects.
The tank designer by calculation will have the shell design thickness. Then based on project specs the design thickness will be added by the corrosion allowance. Sometime the number is odd let say 7.89 mm. The order to steel mill would 8 mm.
During construction many time happen our grinder or helper than learning about grinder will over grinding when they are removing the temporary attachments.
Yes, sometimes we can ask the welder to build up that over grinding area. But also happen we miss to see the other over grinding area.
It can be seen clearly after the tank is painted.
The QC inspector then will point out that area are over grinding so the thickness of the plate is reduced by 1 or 2 mm.
So far I always win by giving the above reason design thickness + corrosion + round up.
How do you see this ?
Your comments is highly appreciated.
This issue always happen in tank construction in my past and current projects.
The tank designer by calculation will have the shell design thickness. Then based on project specs the design thickness will be added by the corrosion allowance. Sometime the number is odd let say 7.89 mm. The order to steel mill would 8 mm.
During construction many time happen our grinder or helper than learning about grinder will over grinding when they are removing the temporary attachments.
Yes, sometimes we can ask the welder to build up that over grinding area. But also happen we miss to see the other over grinding area.
It can be seen clearly after the tank is painted.
The QC inspector then will point out that area are over grinding so the thickness of the plate is reduced by 1 or 2 mm.
So far I always win by giving the above reason design thickness + corrosion + round up.
How do you see this ?
Your comments is highly appreciated.