Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations pierreick on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Design Work in Progress Status Reports 1

Status
Not open for further replies.

hlsodom

Civil/Environmental
Apr 22, 2003
8
Do you have a design Status Report that you are proud of? How do you estimate the percentage of completion?

I am involved in compiling Work in Progress Status reports. Work in progress in this case is percentage of the design project(milestone)work product that has been completed, i.e., the percentage of the fee that has been earned. This estimate is compared to the percentage of the project cost that has been expended to determine how far ahead or behind the project is financially. The reports are produced weekly in time to determine if extra-time will be required over the weekend.

If you have one please describe it or post it.

hlsodom
 
Replies continue below

Recommended for you

The Weekly Status Report is a very good tool to track the progress of a project.

The example I give is that of a Software Project Weekly Status Report but the principles can be applied to any project. What you need to know is: the distinct Stages (milestones) of the project. At start of project itself, or once you have complete the scoping work, allocate percentage completion to each Stage or milestone.

For example in one software project where we designed ISDN software into a existing PSTN code baseline, we had decided that SRS completion: 10% Design completed: 25% Coding completed: 40% Unit Testing over: 50% System Testing Phase I(simulated environment): 65% Feature Testing (actual target): 75% Final build over: 85% System testing by V&V team over: 90% All documents and clean-up over: 100%

As you can see we deliberately down-played the earlier stages and allowed the buffer to be available by including finer granularity in the later stages. This was a small trick which really played us huge dividends: we were able to crash the completion time from Dec to Aug of the year (of course with a great amount of focus from the Top Management).

You can do the same for your project too. Down play those stages that are easy to complete and introduce more granularity into the difficult to do and difffcult to track progress Stages.

The actual template then goes like this:

Sl. | Miletone ID | Percentage of this | Overall project
No. | & description | milestone completed | completion
===========================================================


Then u can have the minute details person-wise as to what percentage of their jobs they need to complete to increase the %age completion of the milestone

Milestone ID: AAAA
==================
Sl. | Person Name | %age to be | Due | New | Actual |Remarks
No. | or Initials | completed | date| Date| Date |
============================================================

The due date is original date of completion as per plan; new date is same as due date usually; in case of problems or issues (which are mentioned in Remarks) then new date may be different from the due date. Actual date is the date of actual completion of the milestone.

Once u have completed a milestone and reported the actual completion date, u can remove it from the subsequent weekly reports. If u r using an XL sheet, u could transfer the
completed milestones to a separate worksheet.

Action Plan to address Issues
=============================
Sl.| Milestone | Issue | Mitigation / | Due | Actual
No.| ID | | Contingency | date | Date
==========================================================

For every Issue identified in the "Remarks" column which affects the due date planned originally, there should be a mitigation or contingency plan prepared. This Action should be accomplished by the Due Date. Once u record the completion of this Action on Actual date, u can then remove that Issue from subsequent Weekly Status Reports.

It is a good idea to just report the next 3 milestones or the next month's milestones in the 'current' XL worksheet name it MMMyy eg Apr03 and is what was just described above.

Have 1 worksheet for 'total' original vs actual completed dates ... the completed dates get filled up as & when the milestones are achieved. This will have the format of

Sl.| Milestone ID | %age | cumulative | Due | Actual
No.| description |completed | completed | Date | Date
==========================================================

This is where u record the initial %ages(percentages) that you are assuming as completion of the milestone with respect to the whole project. If u link up the 2 worksheets, then u could even twaek these percentages if required during the course of your project.

Hope this helps and answers your query,
Peace be upon you,
Naseem Mariam, Project Management Coach,
Project Management Made easy as 123
P.S: There is some shift in the tables headings but I hope that the contents remain legibe; I have used the "|" character to differentiate the fields.
 
Thanks for the cogent advice re: management of project resource time. The advise to break the project down into more milestones with more detail from the middle onwards is insightful.

I still have the problem of presenting the economics of determining the value of the Work in Progress that has been completed but not yet invoiced. The timing the availability of all this data is critical for the milestone estimates to match the payroll/cost data.

What do you do? Are there any case histories?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor