ysna
Geotechnical
- Aug 27, 2015
- 16
Hi,
A client of mine have asked me to suggest and design a retaining wall system for an 18 meter deep excavation next to a series of adjacent 5 to 6 story residential buildings alongside one edge of the excavation site. The problem is, almost 90 percent of excavation to the desired depth have already been completed, and now that there seems to be some excessive settlements near adjacent pavements on three other sides of excavation site, he is concerned about probable collapse of open cut, and asked for a professional advise on the matter. As you can see from attached photo, about 4 to 5 meter of soil width have been kept alongside residential buildings (right side of the photo), but excavation on other three sides of the site are almost completed. There seems to be no sign of excessive settlements on the adjacent buildings, but in other three sides of the excavation, there is signs of local collapses on the face of excavation. You can see some temporary steel shoring elements near those areas. My question is, regarding that other than alongside residential buildings, the excavation is almost completed on three other sides, what is most logical solution for retaining of an already excavated cut face? The soil of the excavation site is moderately to highly cemented medium to fine sand (SP) and construction site is about 70 meter wide and 100 meter long.
A client of mine have asked me to suggest and design a retaining wall system for an 18 meter deep excavation next to a series of adjacent 5 to 6 story residential buildings alongside one edge of the excavation site. The problem is, almost 90 percent of excavation to the desired depth have already been completed, and now that there seems to be some excessive settlements near adjacent pavements on three other sides of excavation site, he is concerned about probable collapse of open cut, and asked for a professional advise on the matter. As you can see from attached photo, about 4 to 5 meter of soil width have been kept alongside residential buildings (right side of the photo), but excavation on other three sides of the site are almost completed. There seems to be no sign of excessive settlements on the adjacent buildings, but in other three sides of the excavation, there is signs of local collapses on the face of excavation. You can see some temporary steel shoring elements near those areas. My question is, regarding that other than alongside residential buildings, the excavation is almost completed on three other sides, what is most logical solution for retaining of an already excavated cut face? The soil of the excavation site is moderately to highly cemented medium to fine sand (SP) and construction site is about 70 meter wide and 100 meter long.