madcowscarnival
Civil/Environmental
- Sep 19, 2013
- 25
Picking up a project to help an Architect we've worked with before. The project dragged out long enough that the original Engineer (also a small shop) picked up a big project and now can't set aside the time to complete. I'm completing a grading plan for the lot and trying to layout a detention pond. The project SWMP calcs are all provided, as well as storage volume.
The storage volume is 3050 cu. ft. for a 0.52 ac lot, peak inflow = 5.6 cfs, peak outflow = 3.7, storm type II. This strikes me as high, but without much familiarity in the calculations, I can't verify the numbers. The principle will be in next week (unreachable), but I would like to know if I should proceed with the work or wait until he can verify.
General opinion, if possible, would be fine. Thank you. If more data is needed, I can provide it.
The storage volume is 3050 cu. ft. for a 0.52 ac lot, peak inflow = 5.6 cfs, peak outflow = 3.7, storm type II. This strikes me as high, but without much familiarity in the calculations, I can't verify the numbers. The principle will be in next week (unreachable), but I would like to know if I should proceed with the work or wait until he can verify.
General opinion, if possible, would be fine. Thank you. If more data is needed, I can provide it.