Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Determining Subsidence

Status
Not open for further replies.

cmichaelson

Civil/Environmental
Oct 7, 2003
2
If I'm digging a shallow trench for some minor construction, and then refill it with the excavated soil, how can I determine the rate at which that soil will settle?

The trench will only be a few feet deep and well above the water table. In addition, there will be no load placed on top of the fill, so I don't think the equations for 1 dimensional soil consolidation apply.
 
Replies continue below

Recommended for you

Provided the contractor compacts the material to at least 95% of optimum dry density determined by an "appropriate" test procedure (ASTM D698 or D1557 in the U.S.), then post-construction settlement should be small. While you could use consolidation theory to evaluate this problem, that's effectively trying to "fine tune with a coarse knob." The fill isn't uniform enough, and you can't adequately predict the likely variations with sufficient accuracy - at least for a 2 ft deep trench.

"Rules of thumb" are more useful in your circumstance: properly compacted clay fill will shrink ("settle") about 2 to 4 percent of it's thickness, while sands will shrink about 1 to 2 percent. Crushed rock will settle about 1/2 to 1 percent. Again - these are rules of thumb, and should be used with caution. Deeper fills require more testing and analysis, particularly if settlement is a major concern.

Why are you worried about settlement?

[pacman]

Please see FAQ731-376 by [blue]VPL[/blue] for tips on how to make the best use of Eng-Tips Fora.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor