Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Difference between work effort and duration

Status
Not open for further replies.

DaveGeneski

Computer
Mar 10, 2006
10
Let me try this question again. Lets say I have one person scheduled from 02/01 to 04/01 to complete a task that will only take them 4 hours. How do I tell project that I am giving them two months to complete a 4 hour task. This same person may have 19 other task for that same period.
 
Replies continue below

Recommended for you

As I described, you set the duration to the calendar duration and input 4 hrs for the work. Your resource utilization should reflect the percentage utilization of about 1.3%

TTFN



 
Status
Not open for further replies.

Part and Inventory Search

Sponsor