Different times for different tasks

Status
Not open for further replies.

smpartch

Nuclear
Aug 18, 2007
1
How do I have certain tasks start at 12:00 pm, 8:00 am, 9:00 am? I need to be able to enter a different start time for each individual task. I was able to change the default start time by going to Tools -- Options -- Calendar, but project does it for all of my tasks....

Thanks
 
Replies continue below

Recommended for you

You were close!!
Try Tools, Options, View Tab, click on the Date Format dropdown and select "Mon 1/28/02 12:33PM".

Use caution with Duration when changing the start time. Example a duration of 1 Day for a task that Starts on Mon 1/28/02 12:00PM will Finish Tuesday 1/29/02 at 12:00PM.

Hope this helps!
~J Black
 