OzEng80
Structural
- Jan 8, 2006
- 147
Hi
I was after some guidance/confirmation for dealing with large total and differential settlements.
I have a couple of two story residential houses (one of reinforced masonry and concrete suspended floor (& basement),& one steel framed) that are to be constructed on reclaimed land comprising of about 10m of fill. The controlled fill obviously flags the horrid ‘P’ classification from the geotech but the shrink swell range provided (20-40mm) is indicative of a class ‘M’ site – 100kPa bearing has been confirmed. This is pretty straight forward except that the total settlement for the site has been estimated as 130mm with a differential of 2/3 of this. I am not sure what to do with these numbers….
I contacted the geotech who provided me with the attached document which provides a formula for determining the relative stiffnesses of the raft and the founding material (clayey sand, Es = 6 MPa). Provided this is greater than 0.5 then the raft can be treated as rigid and differential settlements ignored.
I was going to take a standard ‘M’ raft from AS2870 and assess the stiffness to see if this is adequate then deepen the beams as required. Given there is no ‘strength’ requirement I was going to use the same reinforcing as per AS2870 (for the determined beam depth). Is this the correct procedure for designing the raft? Are there any specific Australian code/commentary/guidelines that I should be looking at? What is the threshold after which this type of analysis should occur?
Thanks for your assistance!
I was after some guidance/confirmation for dealing with large total and differential settlements.
I have a couple of two story residential houses (one of reinforced masonry and concrete suspended floor (& basement),& one steel framed) that are to be constructed on reclaimed land comprising of about 10m of fill. The controlled fill obviously flags the horrid ‘P’ classification from the geotech but the shrink swell range provided (20-40mm) is indicative of a class ‘M’ site – 100kPa bearing has been confirmed. This is pretty straight forward except that the total settlement for the site has been estimated as 130mm with a differential of 2/3 of this. I am not sure what to do with these numbers….
I contacted the geotech who provided me with the attached document which provides a formula for determining the relative stiffnesses of the raft and the founding material (clayey sand, Es = 6 MPa). Provided this is greater than 0.5 then the raft can be treated as rigid and differential settlements ignored.
I was going to take a standard ‘M’ raft from AS2870 and assess the stiffness to see if this is adequate then deepen the beams as required. Given there is no ‘strength’ requirement I was going to use the same reinforcing as per AS2870 (for the determined beam depth). Is this the correct procedure for designing the raft? Are there any specific Australian code/commentary/guidelines that I should be looking at? What is the threshold after which this type of analysis should occur?
Thanks for your assistance!