Gopher13
Structural
- Jun 21, 2016
- 94
All,
We are building a new concrete arms vault inside an existing building. There are existing walls on the north and south side of the vault that we will be pouring up against. There is only about 7.5 inches from the bottom of the existing joist to the top of the new concrete vault roof slab. How do you foresee the contractor pouring the roof slab? Is it possible to pour the slab and set the steel reinforcing without removing the roof deck? Please see the attached drawings. Thanks in advance.
We are building a new concrete arms vault inside an existing building. There are existing walls on the north and south side of the vault that we will be pouring up against. There is only about 7.5 inches from the bottom of the existing joist to the top of the new concrete vault roof slab. How do you foresee the contractor pouring the roof slab? Is it possible to pour the slab and set the steel reinforcing without removing the roof deck? Please see the attached drawings. Thanks in advance.