Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Displaying Calander Days

Status
Not open for further replies.

bjbeck

Structural
Mar 10, 2007
4
I was wondering if there is a way to display actual calender days as a column when the calender set to a 5 day work week. (i.e duration is shown at 227 days for a 5 day work week where the overall calander days would be 384 days)

Any help is appreciated.
 
Replies continue below

Recommended for you

I'm running:

Project Management (Primavera)
Release: 5.0 SP3
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor