Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Does the hydrotest include piping systems that will be connected to the final product?

Status
Not open for further replies.

Stephen Max

Mechanical
Jun 10, 2017
22
Hello,

I am designing a pressure vessel according to Division 1 rules that will eventually be fed steam via a piping system. Does the hydrotest require that the piping be included, or can that be tested independently? Nothing is said about piping in UG-99.

Thanks.
 
Replies continue below

Recommended for you

Piping can be done apart from vessel....use piping code for hydrotest of piping spools. I can recall only one or two times we did entire vessel plus piping for hydro, majority (hundreds) of vessels hydrotested on their own.
See U-1(e) for what is included in scope of vessel (Sec. VIII Div.1)
 
Forgot to mention, the requirements for testing piping along with vessel would be found in piping code.
 
Since the vessel and piping are designed using different ASME Codes, the testings should be followed accordingly for the Code compliance.
 
Thank you for your replies, I appreciate the help.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor