Structures33
Structural
- Feb 22, 2007
- 111
I have a wastewater treatment plant structure near Charleston, SC with basins on 2/3 of length and 2-story building on other 1/3 (common wall between the two). The blower and pump room is in the bottom level of the building. I want to use concrete for as much of the building design as possible given the corrosive environment. The building 2nd floor framing span is 34' clear and I am planning to use precast double tees in lieu of CIP beams/slab. I have not used double tees before and think it may be a good solution for this. I am looking for any guidelines, suggestions, tips on using double tees for this application. For example camber considerations, connections at the joints, topping slab (do I get the precast sections with a topping or do I specify the topping be poured), floor finish considerations for the 2nd floor, etc. The double tees will be framing into 12" thick concrete walls on the exterior of the building.
Thanks in advance for any direction you can provide.
Thanks in advance for any direction you can provide.