schoolie
Structural
- Oct 23, 2005
- 7
Hello,
I have a dowel question for everyone. I am saw cutting an existing slab(150'x240') with a 9' wide x 220' long cut and putting back 18" of reinforced concrete to support some new loads. The existing slab is inside of a building and is also 18" thick; however, the existing slab does not have any reinforcing, which is why I am removing it. I need to epoxy a piece of rebar into both sides of the existing slab at the saw cut to reduce the bearing pressure of the new equipment and reduce the amount of concrete that has to be removed and repoured. I have roughly 1500-2000 lbs/ft of shear across each side of the joint. I planned on putting one dowel at mid-depth. I used SAFE to analyze the new slab with soil springs. Anybody have any suggestions on how to calculate spacing, size and embedment for my dowels? I don't believe shear-friction is an option as the sides of the cut will be nice and smooth.
Thanks in advance.
Schoolie
I have a dowel question for everyone. I am saw cutting an existing slab(150'x240') with a 9' wide x 220' long cut and putting back 18" of reinforced concrete to support some new loads. The existing slab is inside of a building and is also 18" thick; however, the existing slab does not have any reinforcing, which is why I am removing it. I need to epoxy a piece of rebar into both sides of the existing slab at the saw cut to reduce the bearing pressure of the new equipment and reduce the amount of concrete that has to be removed and repoured. I have roughly 1500-2000 lbs/ft of shear across each side of the joint. I planned on putting one dowel at mid-depth. I used SAFE to analyze the new slab with soil springs. Anybody have any suggestions on how to calculate spacing, size and embedment for my dowels? I don't believe shear-friction is an option as the sides of the cut will be nice and smooth.
Thanks in advance.
Schoolie